LATEST DECOKING NEWS
Completion of Decoking Operations At TUPRAS
09 Jul 2009
Welcome to the July monthly newsletter from Crest Environmental Services.
DECOKING OF HEATER F1201
Position of 12" Launcher & Valves. This heater comprised of 2 x 6" Inlets and 4 x 12" Outlets. We commenced the decoking of the 12" pipe and then had to remove the launcher to the second 12" valve to decoke the second outlet.


DECOKING OF HEATER F1101A












Pass A: We removed approximately ½ drum of coke from this pass, we found no problems with any part of this pass.

Pass B: We removed approximately ½ drum of coke from this pass, we found no problems with any part of this pass.

Pass C: We removed approximately 1 ½ drums of coke from this pass, the coke from this pass was contaminated with an oil/slurry.

Pass D: We removed approximately ½ drum of coke from this pass, we found no problems with any part of this pass.